Structural Alterations to a Georgian townhouse
The client wished to modernise the property by removing the main internal load-bearing wall on ground and basement levels.
We carried out a site investigation to investigate the existing construction and designed a new steel frame to replace the existing wall. We then managed the tender process on the client’s behalf, helping them select a reliable and competent builder.
Once the project was on site we monitored the builder’s work, checking the construction was in accordance to our detailed drawings and liased with the local authority’s building control department on their behalf.
The project had an extremely tight schedule that required the site investigation, design, tender and construction periods be completed in a total of three weeks, which we were able to achieve, enabling them to move into the property for Christmas.